The New Library foundation will intersect the copper and fiber optic cables supplying the EMCS, Wellness, and the UC campus buildings with network connectivity. This has required that new cables be placed out of the way of this foundation. The cables have been placed and we will re-connect the supply to these buildings starting and (hopefully ending) December 29th – when there should be the smallest impact. Each building will lose its network connectivity throughout the day while the new fibers are fused & reconnected. We will send out a notification when we have re-established connections. This process should only take 1 day if everything goes smoothly, 2 days if not. Thank you for your patience and understanding.