Resolved
September 16 Status Update: The majority of the new podium equipment has been installed and the room is now functional for class. We will schedule time with our vendor to install the remaining pieces as soon as their schedule allows.
September 13 Status Update: The replacement system is expected to be here next week.
September 11: The A/V control system in the 540 McCallie Building, Room 394 has stopped working. We are working on obtaining a replacement and hope to have the room operational by the end of the week.
Ticket # 23315742